A construction company has contracted with a major university to build a new sports complex. The contract calls for two sports arenas to be built in the next three years. The company will receive $24,000,000 for the project and their engineers originally estimated a total cost to construct the two arenas of $20,400,000. The two arenas are scheduled for completion in May of 2007. If an actual cost of $9,200,000 is expended in 2004, and the engineers estimate another $12,800,000 is to be expended to complete construction, how much income is to be recognized under the percentage-of-completion method in 2004?


A) $836,364
B) $1,163,636
C) $2,000,000
D) $3,600,000