Under a Contract with Bucolic Farms,Agro Excavation,Inc

Question 11

Multiple Choice

Under a contract with Bucolic Farms,Agro Excavation,Inc.,begins digging an agricultural pond.In mid-project,Agro asks for $15,000 over the contract price,claiming an increase in the "cost of doing business." Bucolic agrees but later refuses to pay.Their agreement is


A) unenforceable because Agro's performance was a preexisting duty.
B) unenforceable because Bucolic's promise was illusory.
C) enforceable.
D) unenforceable because its performance is unforeseeably difficult.

Correct Answer:

verifed

Verified