Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2018, are presented below:
Estimated cost to complete: 
- Assuming BCC recognizes revenue over time according to percentage of completion for this contract, the gross profit recognized in 2018 would be (rounded to the nearest thousand) :
A) $6,000.
B) $39,000.
C) $42,000.
D) $45,000.
Correct Answer: