In 2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions) :
-What is the fixed contract price for CCC's project?
A) $120 million.
B) $225 million.
C) $345 million.
D) $349.5 million.
Correct Answer: