Multiple Choice
Suppose the government can pursue up to three projects.The first has benefits of $300 and costs of $270; the second has benefits of $580 and costs of $460; the third has benefits of $90 and costs of $80.Suppose that it costs $0.15 for the government to raise $1 in revenues.Which project should the government pursue?
A) the first project
B) the second project
C) the third project
D) the project with the largest benefit