Technics Inc

Question 90

Essay

Technics Inc.,a manufacturing company,utilizes job order costing.Each division establishes its own estimates regarding overhead,which are as follows:
​
Division A Division B
Total estimated overhead $128,000 $261,000
Total estimated machine hours 16,000 72,500
Total estimated direct labor costs $155,000 $290,000
If Division A allocates overhead on the basis of machine hours,and Division B allocates overhead as a percentage of direct labor costs,what would the predetermined overhead rate be for each division?

Correct Answer:

verifed

Verified

$128,000 / 16,000 = ...