Multiple Choice
Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project. 
A) $16,900
B) $14,900
C) $14,400
D) $13,200
Correct Answer:

Verified
Correct Answer:
Verified