Use the Failure Probability and Consequence Scores Shown in the Table

Question 27

Multiple Choice

Use the failure probability and consequence scores shown in the table to determine the consequence of failure for the project.  Maturity 0.6 Cost 0.2 Complexity 0.8 Schedule 0.3 Dependency 0.6 Reliability 0.2 Performance 0.5\begin{array} { | l | l | l | l | } \hline \text { Maturity } & 0.6 & \text { Cost } & 0.2 \\\hline \text { Complexity } & 0.8 & \text { Schedule } & 0.3 \\\hline \text { Dependency } & 0.6 & \text { Reliability } & 0.2 \\\hline & & \text { Performance } & 0.5 \\\hline\end{array}


A) Greater than 0.7
B) Less than or equal to 0.7 but greater than 0.5
C) Less than or equal to 0.5 but greater than 0.3
D) Less than 0.2