Multiple Choice
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.

-The critical path in PERT analysis is the path with the
A) smallest variance.
B) longest expected completion time.
C) smallest number of tasks.
D) smallest variance and longest expected completion time.
Correct Answer:

Verified
Correct Answer:
Verified