What is the formula for the earliest finish time for activity i?


A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi−1 + ti
D) EFTi = ESTi − ti

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: Exhibit 15.2<br>The following questions employ the AON

Q29: Exhibit 14.13<br>The following questions use the information

Q42: Exhibit 15.1<br>The following questions employ the AON

Q50: Which activities are critical in the following

Q53: Exhibit 14.13<br>The following questions use the information

Q55: What formula should go in cell

Q58: Exhibit 15.2<br>The following questions employ the AON

Q67: Exhibit 15.3<br>The following questions are based on

Q69: Exhibit 15.2<br>The following questions employ the AON

Q72: If we are employing Activity-On-Arc (AOA) network

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines