Multiple Choice
Leek Company predicted that the fixed overhead would be $200,000 in April 2015.Production amounted to 60,000 actual and 50,000 budgeted decks of cards.Each deck takes approximately 0.20 machine hours to produce.The actual overhead costs per machine hour are $25.What is the production-volume variance?
A) $40,000 unfavourable
B) $40,000 favourable
C) $150,000 unfavourable
D) $150,000 favourable
E) $0
Correct Answer:

Verified
Correct Answer:
Verified