Multiple Choice
The variable overhead flexible-budget variance measures the difference between:
A) actual variable overhead costs and the flexible budget for variable overhead costs.
B) actual variable overhead costs and the static budget for variable overhead costs.
C) the static budget for variable overhead costs and the flexible budget for variable overhead costs.
D) None of these answers are correct.