In a job order cost accounting system, the entry to record the flow of direct materials into production is
A) to debit Work in Process, and credit Materials
B) to debit Materials, and credit Work in Process
C) to debit Factory Overhead, and credit Materials
D) to debit Work in Process, and credit Supplies