Question 101

Multiple Choice

Use the information below to answer the following question(s) .
Jim's Computer Products manufactures keyboards for computers. In June, the two production departments had budgeted allocation bases of 10,000 machine hours in Department 1 and 5,000 direct manufacturing labour hours in Department 2. The budgeted manufacturing overheads for the month were $34,500 and $37,500, respectively. For Job 501, the actual costs incurred in the two departments were as follows:
Use the information below to answer the following question(s) . Jim's Computer Products manufactures keyboards for computers. In June, the two production departments had budgeted allocation bases of 10,000 machine hours in Department 1 and 5,000 direct manufacturing labour hours in Department 2. The budgeted manufacturing overheads for the month were $34,500 and $37,500, respectively. For Job 501, the actual costs incurred in the two departments were as follows:    Job 501 incurred 1,000 machine hours in Department 1 and 300 manufacturing labour hours in Department 2. The company uses a budgeted departmental overhead rate for applying overhead to production. -XYZ Company uses a normal job costing system. The direct labour rate is $27 per hour; and, the budgeted indirect cost allocation rate is $20 and uses direct labour hours as the cost allocation base.   What amount should be added to work-in-process control? A)  $12,000 B)  $47,000 C)  $59,000 D)  $76,000 E)  $85,000 Job 501 incurred 1,000 machine hours in Department 1 and 300 manufacturing labour hours in Department 2. The company uses a budgeted departmental overhead rate for applying overhead to production.
-XYZ Company uses a normal job costing system. The direct labour rate is $27 per hour; and, the budgeted indirect cost allocation rate is $20 and uses direct labour hours as the cost allocation base. Use the information below to answer the following question(s) . Jim's Computer Products manufactures keyboards for computers. In June, the two production departments had budgeted allocation bases of 10,000 machine hours in Department 1 and 5,000 direct manufacturing labour hours in Department 2. The budgeted manufacturing overheads for the month were $34,500 and $37,500, respectively. For Job 501, the actual costs incurred in the two departments were as follows:    Job 501 incurred 1,000 machine hours in Department 1 and 300 manufacturing labour hours in Department 2. The company uses a budgeted departmental overhead rate for applying overhead to production. -XYZ Company uses a normal job costing system. The direct labour rate is $27 per hour; and, the budgeted indirect cost allocation rate is $20 and uses direct labour hours as the cost allocation base.   What amount should be added to work-in-process control? A)  $12,000 B)  $47,000 C)  $59,000 D)  $76,000 E)  $85,000 What amount should be added to work-in-process control?


A) $12,000
B) $47,000
C) $59,000
D) $76,000
E) $85,000

Correct Answer: