Answer the Following Questions Using the Information Below

Question 87

Multiple Choice

Answer the following questions using the information below:
Brennen Incorporated planned to use $24 of material per unit but actually used $25 of material per unit, and planned to make 2,000 units but actually made 2,400 units.
-The flexible-budget amount is:


A) $48,000
B) $50,000
C) $57,600
D) $60,000

Correct Answer: