Multiple Choice
The conceptual design phase is the second phase in the systems design life cycle.There are several steps in this phase.Which step listed below is not a valid step made in the second phase of the SDLC?
A) evaluate design alternatives
B) physical systems design
C) prepare a conceptual systems design report
D) prepare design specifications
Correct Answer:

Verified
Correct Answer:
Verified