Nova Construction Company (NCC) entered into a contract to build a school for $1,800,000. Construction commenced on May 1, 2020, with a planned completion date of December 31, 2022. A summary of the related accounting information is provided below: How much gross profit would be recognized in fiscal 2020 if NCC uses the percentage of completion method?
A) $50,000
B) $100,000
C) $130,000
D) $180,000