Nichols Construction Company (NCC)entered into a Contract to Build a Shopping

Question 67

Multiple Choice

Nichols Construction Company (NCC) entered into a contract to build a shopping complex for $1,900,000. Construction commenced on July 1, 2020, with a planned completion date of December 31, 2022. A summary of the related accounting information is provided below: 202020212022 Costs incurred during the year 400,000500,000650,000 Estimated costs to complete at year end 1,200,000600,0000 Billings during the year 560,000640,000600,000 Cash collections during the year 500,000310,000990,000\begin{array} { | l | r | r | r | } \hline & \mathbf { 2 0 2 0 } & \mathbf { 2 0 2 1 } & \mathbf { 2 0 2 2 } \\\hline \text { Costs incurred during the year } & 400,000 & 500,000 & 650,000 \\\hline \text { Estimated costs to complete at year end } & 1,200,000 & 600,000 & 0 \\\hline \text { Billings during the year } & 560,000 & 640,000 & 600,000 \\\hline \text { Cash collections during the year } & 500,000 & 310,000 & 990,000 \\\hline\end{array} How much would the balance in accounts receivable be on the balance sheet of NCC at the end of 2021 if NCC uses the percentage of completion method?


A) $130,000
B) $390,000
C) $790,000
D) $1,100,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions