Multiple Choice
Yang Construction Company entered into a contract to build a new airport terminal for $2,500,000. Construction commenced on August 1, 2020, with a planned completion date of December 31, 2022. A summary of the costs, billings, and collections is provided below: Yang uses the percentage of completion method. How much gross profit would Yang recognize in 2021?
A) $100,000 loss
B) $75,000 loss
C) $50,000 profit
D) $100,000 profit