During the year,Paul Company used a predetermined overhead rate of $3.50 per direct labour hour,based on an estimate of 22,000 direct labour hours to be worked during the year.Actual overhead cost and activity during the year were: 
What was the under- or overapplied overhead for the year?
A) $2,500 overapplied.
B) $2,500 underapplied.
C) $10,500 overapplied.
D) $13,000 underapplieD.
$90,000 - (25,000 @ $3.50) = $2,500 underapplieD.