Ellmann Systems Is Considering a Project That Has the Following r9.00% Year: 0123 FCF: −$1000$500$500$500\begin{array}{lccc}r& 9.00\%\\\text { Year: } &0& 1 & 2 & 3 \\ \text { FCF: } & -\$ 1000 & \$ 500 & \$ 500& \$ 500\end{array}

Question 93

Multiple Choice

Ellmann Systems is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r9.00% Year: 0123 FCF: −$1000$500$500$500\begin{array}{lccc}r& 9.00\%\\\text { Year: } &0& 1 & 2 & 3 \\ \text { FCF: } & -\$ 1000 & \$ 500 & \$ 500& \$ 500\end{array}


A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90