Which accounting method is permitted under ASPE for construction contracts?


A) An accounting method that recognizes revenue and expenses on a cash basis.
B) An accounting method that recognizes revenue and expenses only after it is completed.
C) An accounting method that recognizes costs as incurred and an amount of revenue equal to the costs that are expected to be recovered on the contract.
D) An accounting method that recognizes revenue and expenses based on the fair value of the contract.