A Firm Must Choose Between Two Projects, X and Y

Question 47

Multiple Choice

A firm must choose between two projects, X and Y. Project X has the highest net present value, but project Y has the highest profitability index. The firm should choose project Y if:


A) the firm is a risk seeker.
B) the firm is risk averse.
C) the firm has substantial investment resources.
D) the firm has limited investment resources.