Armati, Inc -Refer to the Figure

Question 4

Multiple Choice

Armati, Inc., is looking for feedback on companyperformance. The company compares the budget for the year with the actual costs. Data have been collected below:
Armati, Inc., had the following budgeted data:
 Unit sales 26,000 Unit production 26,000 Budgeted fixed overhead: $800 Supervision 2,000 Depreciation 100 Rent 1800\begin{array}{lr}\text { Unit sales } & 26,000 \\\text { Unit production } & 26,000 \\& \\\text { Budgeted fixed overhead: } & \$ 800 \\\text { Supervision } & 2,000 \\\text { Depreciation } & 100 \\\text { Rent } & 1800\end{array}

Budgeted variable costs per unit:  Direct materials$0.15 Direct labour 0.20 Supplies 0.02 Indirect labour 0.05Power0.02\begin{array}{llr} \text {Budgeted variable costs per unit: } &\\ \text { Direct materials} &\$0.15\\ \text { Direct labour } &0.20\\ \text { Supplies } &0.02\\ \text { Indirect labour } &0.05\\\text{Power}&0.02\end{array}
 Actual unit sales24,000Actual unit production 28,000 Actual fixed overhead: Supervision $850 Depreciation 2,000 Rent100\begin{array}{llr} \text { Actual unit sales} &24,000\\ \text {Actual unit production } &28,000\\\\ \text { Actual fixed overhead:} &\\ \text { Supervision } &\$850\\ \text { Depreciation } &2,000\\ \text { Rent} &100\\\end{array}

 Actual variable costs: Direct materials $3,500 Direct labour4,900Supplies 530 Indirect labour1,250Power 470\begin{array}{llr} \text { Actual variable costs: } &\\ \text {Direct materials } &\$3,500\\ \text { Direct labour} &4,900\\ \text {Supplies } &530\\ \text { Indirect labour} &1,250\\ \text {Power } &470\\\end{array}


-Refer to the figure.What is the flexible budget for direct materials cost?


A) $3,500
B) $3,600
C) $3,900
D) $4,200

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge