A normal costing system records which costs in work in process?


A) actual direct materials,actual direct labour,actual manufacturing overhead
B) applied direct materials,applied direct labour,applied manufacturing overhead
C) applied materials and labour and actual manufacturing overhead
D) actual materials and labour and applied overhead