Multiple Choice
Upon completing a job,direct materials totaled $3,000; direct labor,$3,500; and factory overhead,$1,500.Units produced totaled 1,000.What is the per unit cost?
A) $8,000
B) $6,500
C) $6.50
D) $8
Correct Answer:

Verified
Correct Answer:
Verified