Matching
Match the following descriptions with the appropriate term.
Premises:
A comparison of actual costs and budgeted costs
A budget representing only one level of activity
An operating plan expressed in monetary units
A budget that shows the budgeted costs at various levels of activity
A budget made for each manufacturing cost
Costs that vary with, but not in direct proportion to, the volume of activity
Costs that do not change in total as the level of activity changes
Used to determine the fixed and variable components of a semi variable cost
The different levels of activity at which a factory is expected to operate
Costs that vary in total in direct proportion to changes in the level of activity
Responses:
Budget
Budget performance report
Fixed budget
Fixed costs
Flexible budget
High-low point method
Manufacturing cost budget
Relevant range of activity
Semi-variable costs
Variable costs
Correct Answer:
Premises:
Responses:
A comparison of actual costs and budgeted costs
A budget representing only one level of activity
An operating plan expressed in monetary units
A budget that shows the budgeted costs at various levels of activity
A budget made for each manufacturing cost
Costs that vary with, but not in direct proportion to, the volume of activity
Costs that do not change in total as the level of activity changes
Used to determine the fixed and variable components of a semi variable cost
The different levels of activity at which a factory is expected to operate
Costs that vary in total in direct proportion to changes in the level of activity
Premises:
A comparison of actual costs and budgeted costs
A budget representing only one level of activity
An operating plan expressed in monetary units
A budget that shows the budgeted costs at various levels of activity
A budget made for each manufacturing cost
Costs that vary with, but not in direct proportion to, the volume of activity
Costs that do not change in total as the level of activity changes
Used to determine the fixed and variable components of a semi variable cost
The different levels of activity at which a factory is expected to operate
Costs that vary in total in direct proportion to changes in the level of activity
Responses:
Related Questions
Q37: The labor standard for a product was
Q38: In a factory, the fixed costs per
Q39: The difference between the total standard cost
Q40: The standard costs for a unit
Q41: Direct factory labor is usually considered to
Q43: In a factory, the fixed costs are
Q44: Deducting the total variable cost from the
Q45: Semi-variable costs are sometimes called mixed costs.
Q46: A budget performance report compares actual costs
Q47: Costs are expected to behave in a