Multiple Choice
Discrepancies between data items recorded by a system and the underlying economic events or objects they represent are a violation of the control goal of:
A) ensure input validity
B) ensure input completeness
C) ensure input accuracy
D) ensure update completeness
Correct Answer:

Verified
Correct Answer:
Verified