Nichols Construction Company (NCC)entered into a Contract to Build a Shopping

Question 82

Multiple Choice

Nichols Construction Company (NCC) entered into a contract to build a shopping complex for $1,900,000.Construction commenced on July 1,2017,with a planned completion date of December 31,2019.A summary of the related accounting information is provided below:
Nichols Construction Company (NCC) entered into a contract to build a shopping complex for $1,900,000.Construction commenced on July 1,2017,with a planned completion date of December 31,2019.A summary of the related accounting information is provided below:   How much would the balance in accounts receivable be on the balance sheet of NCC at the end of 2018 if NCC uses the percentage of completion method? A) $130,000 B) $390,000 C) $790,000 D) $1,100,000
How much would the balance in accounts receivable be on the balance sheet of NCC at the end of 2018 if NCC uses the percentage of completion method?


A) $130,000
B) $390,000
C) $790,000
D) $1,100,000