Early in 2018,Forest Ltd

Question 72

Multiple Choice

Early in 2018,Forest Ltd.signed a contract to construct a warehouse.Forest's management estimated the gross profit on the contract to be $740,000,as indicated by the following:
Early in 2018,Forest Ltd.signed a contract to construct a warehouse.Forest's management estimated the gross profit on the contract to be $740,000,as indicated by the following:   At the end of 2018,the status of the work on the contract was as follows:   How much revenue can be recognized on this contract for 2018,assuming that Forest uses the Percentage of completion basis for long-term construction contracts (round to nearest dollar) ? A) $333,000 B) $863,333 C) $1,575,000 D) $1,711,957
At the end of 2018,the status of the work on the contract was as follows:
Early in 2018,Forest Ltd.signed a contract to construct a warehouse.Forest's management estimated the gross profit on the contract to be $740,000,as indicated by the following:   At the end of 2018,the status of the work on the contract was as follows:   How much revenue can be recognized on this contract for 2018,assuming that Forest uses the Percentage of completion basis for long-term construction contracts (round to nearest dollar) ? A) $333,000 B) $863,333 C) $1,575,000 D) $1,711,957
How much revenue can be recognized on this contract for 2018,assuming that Forest uses the
Percentage of completion basis for long-term construction contracts (round to nearest dollar) ?


A) $333,000
B) $863,333
C) $1,575,000
D) $1,711,957