Multiple Choice
Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?
A) Total time is 10 days,total cost is $2500
B) Total time is 9 days,total cost is $2300
C) Total time is 8 days,total cost is $2750
D) Total time is 8 days,total cost is $1850
Correct Answer: