Multiple Choice
Using the assembly-line balancing procedure,which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4,6,7,2,6,and 5 minutes,and the cycle time is 10 minutes?
A) 3
B) 5
C) 6
D) 8
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified