Multiple Choice
In setting up a Kanban control system you need to determine the number of Kanban card sets needed.If the expected demand during lead time is 50 per hour, the safety stock is 20% of the demand during lead time, the container size is 4.If the lead time to replenish an order is 8 hours, what number of Kanban card sets is needed?
A) 60
B) 80
C) 90
D) 120
E) 150
Correct Answer:

Verified
Correct Answer: