Multiple Choice
If the cost estimate will be the basis for contract awards and performance reporting,it should be a ____ and as accurate as possible.
A) budgetary estimate
B) definitive estimate
C) rough order of magnitude estimate
D) final estimate
Correct Answer:

Verified
Correct Answer:
Verified