After Looking at the PERT Chart for the Development of the New

Question 9

Multiple Choice

After looking at the PERT chart for the development of the new fashion line,Quinn realized that the longest path showed that the project would take a minimum of 60 days.Quinn was able to get this information as a result of the:


A) longest path method.
B) activity path method.
C) critical path method.
D) project path method.