Multiple Choice
_____ will ensure that slack is built into the schedule to accommodate the unexpected,such as incompatibility with previous hardware,heavier than usual sales,or vacations and holidays.
A) Prioritizing resources
B) Long-term objectives
C) Anticipating contingencies
D) Consistent output