Short Answer
In setting up a kanban control system and you need to determine the number of kanban card sets needed.If the expected demand during lead time is 50 per hour,the safety stock is 20% of the demand during lead time,the container size is 4.If the lead time to replenish an order is 2 hours,what number of kanban card sets is needed?