In Setting Up a Kanban Control System You Need to Determine

Question 48

Multiple Choice

In setting up a Kanban control system you need to determine the number of Kanban card sets needed.If the expected demand during lead time is 50 per hour, the safety stock is 20% of the demand during lead time, the container size is 4.If the lead time to replenish an order is 8 hours, what number of Kanban card sets is needed?


A) 60
B) 80
C) 90
D) 120
E) 150

Correct Answer:

verifed

Verified