Which of the following is not a lot sizing technique used in MRP systems?
A) Lot-for-lot (L4L)
B) Economic order quantity (EOQ)
C) Least total cost (LTC)
D) Least unit cost (LUC)
E) Two-bin system (TBS)
Correct Answer: