Which of the Following Is the Planned-Order Release Using an MRP

Question 21

Multiple Choice

Which of the following is the planned-order release using an MRP program if the gross requirement is 5,000 and the inventory on hand is 1,200?


A) 5,000
B) 4,500
C) 3,800
D) 1,200
E) None of the above