Which Statement Concerning MRP II Is False

Question 17

Multiple Choice

Which statement concerning MRP II is false?


A) It is basically a computerized system.
B) It can handle complex planning and scheduling quickly.
C) It involves other functional areas in the production planning process.
D) It involves capacity planning.
E) It produces a production plan which includes all resources required.