Question 128

Essay

A manager intends to order a new machine and must now decide on the number of spare parts to order along with the machine. The parts cost $400 each and have no salvage value. The manager has compiled a frequency distribution for the probable usage of spare parts, as shown:  Usage  Frequency 0.081.302.243.204.18\begin{array} { l l } \text { Usage } & \text { Frequency } \\\hline 0 & .08 \\1 & .30 \\2 & .24 \\3 & .20 \\4 & .18\end{array} For what range of shortage costs would stocking one spare part constitute an optimal decision?

Correct Answer:

verifed

Verified

Ce = $400
In order for a stocking level o...