Multiple Choice
Actual fixed overhead is $33,300 (12,000 machine hours) and fixed overhead was estimated at $34,000 when the predetermined rate of $3.00 per machine hour was set.If 11,500 standard hours were allowed for actual production,applied fixed overhead is
A) $33,300.
B) $34,000.
C) $34,500.
D) not determinable without knowing the actual number of units produceD.