In an MRP Problem, a Is an MPS Item

Question 44

Multiple Choice

In an MRP problem, A is an MPS item.Every A requires 2 B's and 3 C's.Every B requires 5 C's. All lead times are two periods.Initial inventory values for A is 100, B is 200 and C is 0.Use lot-4-lot method for order quantities for all items.If gross requirement for A is 800 in period 9, what will be the planned order release for B in period 5?


A) 1600
B) 1400
C) 700
D) 800
E) 1200