The Bottom-Up Method of Estimating Where Work Package Time and Costs

Question 98

Short Answer

The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________ method.

Correct Answer:

verifed

Verified

template
Explanation: If the project is ...