Multiple Choice
While it may be true that Mega Projects are by nature extremely difficult to estimate, another factor identified in the consistent pattern of estimating difficulties is:
A) Unidentified risks.
B) Deception.
C) Economic downturn.
D) Both unidentified risks and economic downturn.
Correct Answer:

Verified
Correct Answer:
Verified