A Contractor Finished a Bridge Across a Lake 18 Months

Question 57

Multiple Choice

A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by


A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.

Correct Answer: