Multiple Choice
Which of the following factors should be considered when a project team evaluates a "make or buy" decision to procure services?
A) prevailing public opinion regarding the economic impact of outsourcing
B) only the direct costs associated with the decision,excluding consideration of indirect costs
C) advantages and disadvantages of outsourcing in terms of time,cost and performance control
D) project manager's or sponsor's preference
Correct Answer:

Verified
Correct Answer: