The Approved Time-Phased Project Budget,excluding Any Management Reserves,which Can Be

Question 29

Multiple Choice

The approved time-phased project budget,excluding any management reserves,which can be changed only through formal change control procedures and is used as a basis of comparing actual results,is called a ____:


A) measurement baseline.
B) cost baseline.
C) cost benchmark
D) control account

Correct Answer:

verifed

Verified