A company runs an assembly line two shifts a day; however,the first shift runs the line 7.5 hours and the second shift runs the line 9 hours.The machine has a maximum output of 120 units per hour.Over the last 28 shifts,the first shift averaged 825 units a shift and the second shift averaged 972 units.Which shift better utilizes the machine?
Correct Answer:

Verified
First shift utilization = 825 units per ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q64: For machines,the peak capacity is also known
Q65: In a typical experience curve,the time per
Q66: Which is not an approach for maximizing
Q67: Capacity strategies refer to all of the
Q68: Why should services be near to the
Q70: Capacity is only measured in terms of
Q71: Meals served would not be an appropriate
Q72: Uncertain demand requires cushion capacity.
Q73: Utilization is the ratio of what variable
Q74: A small hamburger stand has seating for